• Call us today - (309) 647-7400

WIU Steam Line Renewal Bid Package 2 Western Illinois University

Macomb, IL



Quick Facts:

Owner; Western Illinois University
Engineer: Affiliated Engineers, Inc.
Cost: $4,034,811.69
Superintendent: Roger Carlson
Project Manager: Chris Booher

Project includes second phase of upgrades and additions to the existing Western Illinois University steam and condensate distribution network. Construction includes utility location efforts, utility relocation, tree protection, excavation and backfill for the construction of 2,500 LF of precast concrete steam box conduit and 8 poured-in-place concrete steam valve vaults. Project runs along University Avenue connecting Phase 1 with Tanner and Henninger Halls and under separate contracts includes mechanical and electrical At the completion of the project the construction work will be backfilled and the site restored to existing connections.