Contract Amount: $5,702,600
Prophetstown Water Treatment Plant & Well No. 5
The Prophetstown Water Treatment Plant & Well No. 5 project involved the construction of a new water treatment facility to serve Well No. 11, along with associated site and utility improvements.
Scope of Work Included:
-
Construction of a new 3,590 SF water treatment plant building
-
Drilling of a new sand and gravel well and installation of a 500 GPM vertical line shaft pump
-
Furnishing and installation of a 600 GPM iron and manganese removal gravity filter
-
Installation of chemical feed systems and equipment
-
Furnishing and installation of process piping, valves, and meters
-
Complete electrical and HVAC systems installation
-
Installation of water system controls and automation
-
Landscaping and seeding
-
Installation of site watermain, valves, fire hydrants, sanitary sewer, and manholes
-
Demolition of the existing water treatment plant
-
Replacement of the motor on Well No. 4 and modification of piping to connect to the new plant
-
Demolition of the existing Well No. 3 building and abandonment of Well No. 3
The project delivered a new, state-of-the-art water treatment facility designed to blend with its surroundings — featuring a residential-style building exterior that complements the neighboring homes in the area.